Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
  • if market-rate construction is delayed, will the affordable housing also be delayed?
  • if so, what happens to the June 2014 agreement, reached by New York State and some community community negotiators, to guarantee--with penalties--the 2,250 units of affordable housing by May 2025, "subject to extensions set forth in the Development Agreement and the General Project Plan"? 
  • will affordable housing be built on sites previously planned for market-rate housing?
  • will covering the railyard for vertical construction be delayed? And doesn't that prolong blight?
  • how much tension is this causing between Forest City and its Shanghai-based partner?
  • beyond the three sites already up for sale/new investment, how much more might be sold?
  • will the developers seek more subsidies, or relaxed terms regarding the affordable housing?
Annotations as of October 2016
The announcement

According to the news release, Forest City, for the three months ended September 30, 2016, had a net loss of $430.9 million, or $1.67 per share, compared with a net loss of $302.2 million, or $1.18 per share, the previous year, mainly due to increased impairments:
The third-quarter net loss includes an impairment of non-depreciable real estate of $307.6 million, primarily related to Pacific Park Brooklyn. During the quarter, in light of changing market conditions directly impacting the Brooklyn residential market, the company, as part of a formal strategic plan update, made the decision to revise the overall project schedule to delay future vertical development. Given these market conditions and project timing, the company updated its estimated revenue, expense, cost and timing assumptions in its discounted cash flow model to estimate fair market value. The updated estimates no longer exceeded the carrying value of the asset, triggering the need for impairment. After the impairment, the company's remaining basis in its aggregate investment at Pacific Park Brooklyn is not material on a GAAP basis.-
(Emphasis added)

Note that Forest City, which is the minority partner in Pacific Park, had to jointly agree with joint venture partner/overseer Greenland USA, which owns 70% of the project/development rights going forward (excepting the arena and the 461 Dean tower). But no mention was made of a joint decision.

In a supplemental document filed with the Securities and Exchange Commission, the developer said that, regarding Pacific Park, it recorded "an impairment of $299.3 million ($266.0 million and $33.3 million allocated our projects under development and projects under construction, respectively."

CEO commentary

"We also recognized a significant impairment of Pacific Park Brooklyn as a result of our decision to revise the project schedule and related assumptions in light of evolving market conditions, including the impact of increased apartment supply, uncertainty surrounding 421A tax abatement and continued escalation in construction and trade costs," Forest City CEO David LaRue said in the statement.

In a separate 10-Q document filed with the SEC, the company added more explanation, acknowledging that the 550 Vanderbilt condo building is delayed:
During the three months ended September 30, 2016, it became evident the occupancy and rental rate declines in the Brooklyn market was determined not to be temporary as a result of an increased supply of new rental product amplified by the sun-setting and the uncertainty around the 421 A real estate tax abatement program. Over the last quarter, the condominium market in New York has also softened, causing the projected sale schedule for 550 Vanderbilt to be adjusted accordingly. Separately, the construction costs across the New York market continue to trend upward, resulting in increases in the estimated trade costs for certain infrastructure as well as vertical construction. In addition, the expiration of and the continued uncertainty related to the availability of the 421 A real estate tax abatement program puts further stress on anticipated returns.. the Company updated the discounted cash flow model to reflect the updated timing of the project schedule as well as the revenue, expense and cost assumptions. Based on the above, the estimated fair value of the investment no longer exceeded the carrying value. As a result, the Company recorded an other-than-temporary impairment of$299,300,000 during the three months ended September 30, 2016. The remaining basis in the investment (net of estimated future funding obligations) is not material.
No updated schedule was announced, but presumably there will be questions during today's conference call with investment analysts.

"While the Pacific Park Brooklyn impairment is a disappointment, revising the schedule to delay additional future vertical development reflects the tough decisions that are part of our disciplined approach to capital allocation," LaRue said. "As we have said before, we will activate new opportunities from our pipeline of entitlements only when and where we believe we can achieve an appropriate risk-adjusted return."

He made no mention of the affordable housing deadline.

Under construction

The press release cites three Pacific Park properties under construction:
  • 535 Carlton, a 298-unit, all-affordable apartment community, is expected to begin phased opening in the fourth quarter of 2016.
  • 550 Vanderbilt, a 278-unit condominium property, is expected to begin phased opening in the first quarter of 2017.
  • 38 Sixth Avenue, a 303-unit, all-affordable apartment community with 6,000 feet of street-level retail, is expected to begin phased opening in the second quarter of 2017.
There seem to be some delays, however. A separate 10-Q document filed with the SEC offers the following timetable. Note that "100% affordable" 535 Carlton could take a year to fill up, until the fourth quarter of 2017, as could the similar 38 Sixth Avenue, starting in the second quarter of 2017. Meanwhile 550 Vanderbilt is supposed to open in the first three quarters of 2017.


Is modular tower open?

The document, oddly enough, said that, in the third quarter of this year, Forest City opened two new properties, including "461 Dean Street, a 363-unit apartment community at Pacific Park Brooklyn."

Actually, it's by no means open. The Supplemental document says construction is complete and that, as of 9/30/16, 160 of the 363 units had received a certificate of occupancy.

According to p. 50 of the Investor Presentation below, as of 10/27/16, the developer has a 3% lease commitment at 461 Dean. Presumably that applies to the 50% market-rate units, and/or the retail, not the 50% below-market "affordable" units, for which there was a lottery.


Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming + FAQ (post-dated pinned post)

This graphic, posted in January 2018, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

How many people are expected?

Atlantic Yards/Pacific Park has a projected 6,430 apartments housing 2.1 persons per unit (as per Chapter 4 of the 2006 Final Environmental Impact Statement), which would mean 13,503 new residents, with 1,890 among them in low-income affordable rentals, and 2,835 in moderate- and middle-income affordable rentals.

That leaves 8,778 people in market-rate rentals and condos, though let's call it 8,358 after subtracting 420 who may live in 200 promised below-market condos. So that's 5,145 in below-market units, though many of them won't be so cheap.

As …

The passing of David Sheets, Dean Street renter, former Freddy's bartender, eminent domain plaintiff, and singular personality

David Sheets, longtime Dean Street renter, Freddy's bartender, eminent domain plaintiff, and singular personality, died 1/17/18 in HCA Greenview Hospital in Bowling Green, KY. He was 56.

There are obituary notices in the Bowling Green Daily News and the Wichita Eagle, which state:
He was born in Wichita, KS where he attended public Schools and Wichita State University. He lived for many years in Brooklyn, NY, and was employed as a legal assistant. David's hobby was cartography and had an avid interest in Mass Transit Systems of the world. David was predeceased by his father, Kenneth E. Sheets. He is survived by his mother, Wilma Smith, step-brother, Billy Ray Smith and his wife, Jane all of Bowling Green; step-sister, Ellen Smith Alexander and her husband, Jerry of Bella Vista, AR; several cousins and step-nieces and step-nephews also survive. Memorial Services will be on Monday, January 22, 2018 at 1:00 pm with visitation from 10:00 am to 1:00 pm Monday at Johnson-Vaughn-Phe…

Some skepticism on Belmont hockey deal: lease value seems far below Aqueduct racino; unclear (but large?) cost for LIRR service

As I wrote for The Bridge 12/20/1, The Islanders Say Bye to Brooklyn, But Where Next?, the press conference announcing a new arena at Belmont Park for the New York Islanders was "long on pomp... but short on specifics."

Notably, a lease valued at $40 million "upfront to lease up to 43 acres over 49 years... seems like a good deal on rent for the state-controlled property." Also, the Long Island Rail Road will expand service to Belmont.

That indicates public support for an arena widely described as "privately financed," but how much? We don't know yet, but some more details--or at least questions--have emerged.

An Aqueduct comparable?

Well, we don't know what the other bid was, and there aren't exactly parcels that large offering direct comparables.

But consider: Genting New York LLC in September 2010 was granted a franchise to operate a video lottery terminal under a 30 year lease on 67 acres at Aqueduct Park (as noted by Gov. Andrew Cuomo).

As…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…